The six modular classrooms we have been expecting will be moved into place during the week of May 5, 2025. During this time, you can expect the following:
- Work will primarily occur on the northwest side of the school.
- The day the modulars are delivered, crews will place them in their designated locations.
- Once complete, the six modulars will be connected as a pod, but the pod will be freestanding/separate from the school.
- While modulars are being delivered, the playground will be closed off to provide enough space for the work to be completed. The playground will reopen once the delivery is completed.
- Parking availability along Falshire Dr. NE will be impacted between Monday May 5 to Wednesday May 7.
- Throughout the spring, work will continue to prepare the new classrooms, which are expected to be ready for the 2025-26 school year.
During the modular delivery, crews will be using the fire lane to access the school site. We ask that parents/guardians to be extra conscious of this during drop-off and pick-up times.
Student and staff safety remains our top priority. The construction area will be securely fenced, and all work during school hours will be carefully managed to minimize disruptions.
We understand these temporary adjustments may cause some inconvenience, and we sincerely appreciate your patience and cooperation. Thank you for your support as we enhance our school community.
If you have any questions about this work, please email facilityprojects@cbe.ab.ca.